![]() |
||||||
| Soil | “To ensure existing soil contamination does not preclude ongoing use of the site for industrial purposes or pose unacceptable risks to the use of the site or the environment.” | |||||
| Groundwater | “To facilitate natural attenuation of the groundwater contamination by treating on-site hot-spots to reduce contaminant concentrations to a level that does not inhibit natural attenuation .” | |||||
|
We believe we can meet these objectives through the aim of removing contaminants from the dry rock and soil between the ground surface and the top of the upper aquifer, and also from the upper aquifer itself. We plan to
target our treatment of the contamination in the hot-spots.
If we can reduce contaminant levels in these areas, the groundwater plume
may reduce as microbes "eat" the remaining contaminants. What treatment options were examined?During 1997, we examined the following treatment options:
Each option was examined for the potential to remove any "pure" contaminants, limit the movement of dissolved contamination, net environmental benefit, likely time of operation, EPA requirements and whether the option would assist in restoring the suitability of the water for stock watering. The EPA has identified that this potential beneficial use for the groundwater needs to be protected. Can the contamination be removed?Since the commencement of groundwater treatment in 2001 the groundwater treatment system has successfully removed contaminants from groundwater beneath the site (refer to the EDC recovery graph). The success of the GWTS in treating the contamination has reduced the concentration a level where the breakdown of contaminants by the microbes is possible. Refer to Monitoring of Treatment. How were contaminants being removed and treated?Air was being blown into the upper aquifer at each of the hot-spots. This rises through the groundwater and brings contaminants with it. The air blown in, and the contaminants it collects, were then removed from the dry rock above the aquifer with suction pumps. The contaminated air was then filtered to remove moisture and then oxidised in an above-ground treatment system.
Was removing the contamination dangerous to human health or the environment?The discharge of air from the treatment system was licensed by the EPA to ensure there were no impacts on people or the environment. The discharges were monitored to ensure compliance with the EPA licence.
How long will it take to remove the contamination?This is still unknown. The groundwater treatment system was in operation from early 2001 until mid 2010, and was proven effective in removal of contaminants from groundwater at the site. A comparison of the extent of contamination in 1997 with the most recent monitoring data clearly shows a significant reduction in the amount of contamination at the site. See monitoring and treatment.
What groundwater treatment results have been achievedPlease refer to Monitoring of Treatment for the most recent groundwater information. Will the method of treatment change?If the methods we are using are not effective, we will discuss options with the Soil and Groundwater Review Group, and the appointed anvironmental auditor. See environmental audit for further details. What contingency plans exist?Should adverse monitoring results be recorded or the treatment of 'hot-spots' have limited success a number of contingency and containment options have been established including: continued natural degradation and monitoring; installation of a treatment system across the extent of the contaminant plume; and installation of an interception system to prevent further off-site movement of the contaminant. What monitoring will occur in the future?The existing groundwater monitoring programme will continue. Eventually we hope to reduce sampling frequency as the contamination levels decrease in response to action to eliminate the hotspots. Groundwater well treatment networkIn September 2005 a review of air sparge performance found hot spot treatment was most effective around functioning air sparge wells, with contaminant trends declining and little evidence of rebound. Based on these findings, enhancements of the existing air sparge and soil vapour extraction well network to treat the remaining contaminant hot spots was recommended. In April 2006 twelve new air sparge wells (to 16 metres depth) and seven new soil vapour extraction wells (to 8.5 metres depth) were drilled and installed. Locations of new wells target the dissolved-phase chlorinated hydrocarbons impacts in the upper basalt aquifer in the vicinity of the former EDC bund and along the southern site boundary. There are
now a total of seventeen air sparge wells and eighteen soil vapour extraction
wells, which will be operated in phases to allow a more targeted approach
to groundwater treatment. The way forwardFollowing shutdown of the treatment system a period of monitoring will be undertaken to measure the effect of natural attenuation on the level of contaminants and to measure how the contamination levels change over time. Recommendations for future treatment if necessary will be made on the back of this assessment. How is the contaminated soil being treated?With the approval of the EPA and in consultation with the Soil & Groundwater Review Group a soil treatment trial was conducted from May to July 2006. The trial focused on known soil contamination in the south-west corner of the site where tar residue was stored. The benefits of this approach avoid releases of contaminants to atmosphere and reduce OH&S exposure issues as well as avoiding costly off-site treatment and disposal costs. The approach involved ‘ripping’ the soil with an excavator and capturing vapours in perforated piping under a heavy plastic cover. The vapours were extracted from the soil into the soil vapour extraction system for treatment in the GWTS. 2006 soil treatment trial demonstrated soil “ripping” to be an effective soil treatment technology for application at the Altona Propeties site.
How long will it take to treat the soil? Soil treatment at the Altona Properties site is currently 90% complete and the project is expected to reach completion during 2012. |
||||||